Final phase of downtown renovations

Part of the renovations will include a new sidewalk along Selkirk Avenue, between 225th and 226th streets. - Phil Melnychuk/THE NEWS
Part of the renovations will include a new sidewalk along Selkirk Avenue, between 225th and 226th streets.
— image credit: Phil Melnychuk/THE NEWS

A few more of the final pieces of the downtown puzzle will fall into place in the fall.

The District of Maple Ridge held an open house Thursday to preview the plan for rebuilding the stretch of Lougheed Highway from 224th to 226th streets.

The project, yet to be costed out, will complete the downtown renovations started a few years ago that included rebuilding 224th St. from Dewdney Trunk Road to Lougheed Hwy., as well as rebuilding Lougheed from 222nd 224th streets and from 226th to 228th streets.

“From 222nd St., it’s just a continuation of that. Same street trees, same sidewalk,” said Rachel Ollenberger, with the district.

The project entails repaving Lougheed and rebuilding and widening the sidewalk, in sections to the standard three metres. New trees will be planted with underground structures that will speed growth and prevent roots from heaving the sidewalks.

“We will have the wagon wheel crosswalks which people seem to like so much,” added Ollenberger.

She was referring to the circular motif that characterizes the sidewalk lines in the rebuilt sections.

New street lights and furniture identical to that which has been installed on the previous sections will follow.

Costs to complete the two-block section of Lougheed, which will then link to the section rebuilt last year in front of Chances Maple Ridge community gaming centre, haven’t been determined yet.

A completion date hasn’t been set either, only that it will be sometime next year.

Part of the same project and due for completion this fall is the construction of a new sidewalk on the south side of Selkirk Avenue, between 225th and 226th streets.

Currently, there’s only a sidewalk for a part of that distance.

“Selkirk will start to look like a street,” said Ollenberger.

New trees and street lights and hanging baskets will be part of the new sidewalk.

The new sidewalk will continue around the corner of 226th St. on the east side, up to the highway.

The district says the intent of the project is to increase livability and support business growth in the downtown, while improving conditions for pedestrians and shoppers.

Improvements are also scheduled for Edge Street at Dewdney Trunk Rd.

Jackie Chow, of the local cycling group HUB, wants Lougheed Hwy., through the downtown, narrowed to two lanes, bordered by bicycle lanes on either side. Doing so would allow preservation of the parking lanes and could “dramatically improve the shopping experience and vibrancy of Lougheed,” she said on Facebook.

However, she added, the group has been told that traffic volumes are too high on Lougheed Hwy. and that it isn’t part of the cycling network.

 

We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.

You might like ...

TIMELINE: An interactive history of terrorist attacks and plots in Canada
 
B.C. Muslim Association speaks out on gunman
 
How sprawl could rule elections
Metro Vancouver rejects water subsidies for farms
 
Roadside suspensions credited for cut in drunk driving deaths
 
UPDATE: 2 confirmed dead in Marysville, Washington school shooting
Local charity joins fight against Ebola
 
Candidates make pitch to voters in Richmond
 
ELECTION 2014: Tax plan draws opinions at Richmond forum

Community Events, October 2014

Add an Event

Read the latest eEdition

Browse the print edition page by page, including stories and ads.

Oct 24 edition online now. Browse the archives.