Four new storage tanks have been constructed at Trans Mountain’s Edmonton terminal to prepare for opening of the oil pipeline expansion from Alberta to Westridge Terminal in Burnaby B.C. (Trans Mountain)

Trans Mountain begins laying Alberta pipeline for expansion

Construction continues at Westridge terminal in Burnaby B.C.

Trans Mountain Corp. has begun laying pipe across the Alberta segment of its oil pipeline twinning project, expecting to have the first pipe welded, tested and buried by Christmas.

Construction so far has included completion of four new storage tanks at the federal government-owned company’s Edmonton Terminal, and continued work on the Westridge Terminal facilities at Burnaby to accommodate additional tankers for exporting crude.

Pipe is being assembled on the Greater Edmonton section, with clearing, grading, utility relocation and worksite preparations for a series of tunnel-bored sections. Horizontal drilling is planned for 13 sections on the Alberta side of the project, to cross watercourses, railways, major roads, sensitive environmental areas and urban areas, Trans Mountain said in its latest project update.

Trenchless construction is also expected to play a large role in the B.C. section of the project, where thousands of property owners have moved in along the right-of-way since the original Trans Mountain was built in 1954.

Trenchless construction is also expected to play a large role in the B.C. section of the project, where thousands of property owners have moved in along the right-of-way since the original Trans Mountain was built in 1954 to supply refineries at Burnaby and Washington state as well as tanker exports from Burnaby.

RELATED: CEO promises ‘the best darn pipeline in the world’

RELATED: Indigenous leaders choose pipelines over poverty

RELATED: Oil-by-rail traffic rises as B.C. battles Trans Mountain

The B.C. government has continued to oppose the Trans Mountain expansion, supported by Washington Gov. Jay Inslee, despite increased crude by rail coming through Alberta and B.C. to Washington since the existing Trans Mountain line became over-subscribed.

In a year-end interview with Black Press, B.C. Premier John Horgan acknowledged that construction is likely to intensify an already acute shortage of skilled construction workers, as work camps and gas pipeline spreads take shape across northern B.C. to supply the LNG Canada project from Dawson Creek to Kitimat.

B.C. is using a union-only construction model to build the Kicking Horse Pass and other sections of the Trans-Canada Highway from Kamloops to the Alberta border, as well as replacing the Pattullo Bridge and building the Broadway subway line in Metro Vancouver. A skilled labour shortage is driving up costs on those projects, Horgan said.

“And at the same time we have private sector projects like LNG Canada, and potentially the Trans Mountain pipeline, that are going to be taking a whole bunch of workers out of play when it comes to public contracts, and that’s a challenge for government,” Horgan said.

From the Greater Edmonton section, the Trans Mountain right of way goes to Edson, Hinton, Spruce Grove, Stony Plain and Wabamun before reaching the Jasper-Mount Robson stretch where twinning was done a decade ago.

Entering B.C. in the North Thompson region, the pipeline route goes by Avola, Barriere, Blue River, Clearwater, Valemount and Vavenby, where the forest industry has been wound down due to market conditions and loss of lumber to beetle infestations and fires.

At West Barriere, another existing expansion section will be tested and activated, running from a pump station north of Barriere to a new Black Pines pump station north of Kamloops. From there the project goes past Kamloops and Merritt, then down the Coquihalla Pass to Hope.

The project proceeds down theFraser Valley through Chilliwack, Abbotsford and Langley, then into the heavily populated Lower Mainland through Langley, Surrey, Coquitlam and Burnaby.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureTrans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

B.C. Green Party leader Sonia Furstenau outlines her party's climate action platform at Nanaimo's Vancouver Island Conference Centre earlier this month. (News Bulletin file photo)
Green leader Furstenau declared victor in her home riding on Vancouver Island

Cowichan Valley voters elect freshly minted party leader for her second term

John Horgan has been re-elected the MLA for Langford-Juan de Fuca. (File-Black Press)
Horgan trounces challengers to be re-elected in his Vancouver Island riding

MLA has represented constituency of Langford-Juan de Fuca and its predecessors since 2005

An employee at the Pitt Meadows Superstore tested positive for COVID-19. (Black Press files)
Team member at Pitt Meadows Superstore tests positive for COVID-19

The person last worked a shift at the grocery store on Monday, Oct. 19

(Black Press Media files)
Maple Ridge, Pitt Meadows, Katzie Seniors Network keeps elders informed on how to vote

Rides to polling stations hard to come by, but many long term care homes have stations set up within

(Image by Ulrike Leone from Pixabay)
QUIZ: A celebration of colour

Fall in British Columbia is a time to enjoy a spectrum of vivid colours

Canada’s Chief Public Health Officer Theresa Tam responds to a question during a news conference Friday October 23, 2020 in Ottawa. Canada’s top physician says she fears the number of COVID-19 hospitalizations and deaths may increase in the coming weeks as the second wave continues to drive the death toll toward 10,000. THE CANADIAN PRESS/Adrian Wyld
Canada’s top doctor warns severe illness likely to rise, trailing spike in COVID-19 cases

Average daily deaths from virus reached 23 over the past seven days, up from six deaths six weeks ago

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

BC Hydro map showing where power has been knocked out is dotted with over a dozen outages. (BC Hydro map screenshot)
Thousands without power in Lower Mainland on election day

One outage in Langley and Surrey is affecting over 4,000 customers

file
One dead after fiery crash near Agassiz

Agassiz RCMP report a 56-year-old man died Friday night

The possibility of the Canadian Premier League expanding to the Fraser Valley has been floated online. (Facebook photo)
Canadian Premier League possibly eyeing Fraser Valley expansion

Soccer league looking to add ninth team to the mix, B.C. markets potentially rumoured

Most Read