$3.5 billion Massey Bridge will come with tolls

Toll to be similar to Port Mann, expected to result in 13 per cent of traffic diverting to free crossings

Image from video rendering of what new Massey Bridge may look like.

Image from video rendering of what new Massey Bridge may look like.



Building a new bridge to replace the George Massey Tunnel is estimated to cost $3.5 billion and Transportation Minister Todd Stone says it will be tolled, with motorists paying a similar amount as they do at the Port Mann Bridge.

Transportation ministry officials laid out details of the project, which will include the 10-lane bridge over the Fraser River and improvements to 25 kilometres of Highway 99, including three rebuilt interchanges. Two of the bridge lanes will be HOV/transit lanes.

“Wait times today are unacceptable and they are projected to get worse,” Stone said at a briefing in Richmond.

The project definition report claims commuters will save up to 30 minutes if they pay to cross the new bridge but it also projects 14 per cent of current traffic will divert to the Alex Fraser bridge to avoid tolls.

Officials admit that will mean even heavier congestion at the Alex Fraser Bridge as a result, but Highway 99 motorists will ultimately face the same choice as those at Highway 1 – pay in cash for a quicker crossing or wait at the free one.

Stone said he remains committed to exploring bridge toll reforms if both the new Massey and Pattullo bridges end up being tolled.

“We want to hear from British Columbians on the toll, including any thoughts people have on tolling from a regional perspective,” he said, hinting that it may make sense to toll the Alex Fraser.

“You could perhaps provide a lower toll on more crossings,” he said. “Tell us what you think about that.”

Critics argue the new bridge will simply move a major bottleneck up Highway 99 to the Oak Street Bridge.

But traffic counts show more than 60 per cent of northbound traffic crossing the tunnel is headed to and from Richmond, not on to Vancouver.

And the project rationale also cites projections of dramatic population growth South of the Fraser in the decades ahead.

The combined population of Surrey, Delta, Richmond and White Rock is projected to rise 51 per cent to 1.2 million by 2041, and the number of jobs in the same area are to climb 58 per cent.

The 76-page business case – 18 months overdue but now released – assumes a $750 million initial injection of capital from private partners, to be paid back by government later.

It concludes the project can be paid off with tolls over 35 to 60 years.

Stone said the province is seeking federal contributions for the new bridge – which is its top priority for infrastructure grants – and it’s also asking Port Metro Vancouver to make a contribution because eliminating the tunnel will help open up the Fraser River to more shipping.

A hefty federal grant could be used to reduce the expected toll, Stone said, or shorten the expected repayment period.

The project has not yet got Treasury Board approval on the business case, which would mark the final go/no go decision point for the government. The province intends to solicit bids for the project in the spring.

An environmental review is still required as well as Agricultural Land Commission approval to use some protected farmland.

The province is aiming for a 2017 construction start and 2022 completion date for the Massey Bridge.

The province has so far spent about $30 million on the project.

B.C.’s auditor general is conducting an audit to evaluate the quality of the evidence used to support the decision to replace the tunnel and the Opposition maintains the province has pushed ahead with little justification.

“The real worry here is that the choice of this government is to build one large megaproject rather than deal with all of the transit needs in the region,” said NDP transit critic George Heyman.

“We haven’t seen the promised tolling review. We’re just seeing another bridge with more tolls added.”

He questioned whether a federal contribution to the bridge might come at the cost of more money for improved transit.

Delta South independent MLA Vicki Huntington also said the province should move faster to decide how it would make tolls more fair to all motorists crossing the Fraser.

“It’s putting the people south of the Fraser at a huge disadvantage,” she said. “I hope we start evening out these costs to the public.”

Huntington accused the government of ignoring the fact the tunnel has an estimated 50 years of life remaining under a rehabilitation scenario.

“It needs significant renovation and upgrading, which they did to do the Lions Gate Bridge if you remember,” she said. “But they wanted to ignore that. So they’ve made a deliberate decision to put a new bridge in.”

A phase 1 seismic upgrade was performed on the tunnel about 10 years ago, partially strengthening it, but not to a full modern standard. The estimated risk of the tunnel failing in an earthquake is one in 275 years, compared to one in 2,475 years with a new bridge.

Meanwhile, the Port Mann has not generated the traffic levels and tolls originally expected and traffic counts on Highway 99 have recently been decreasing even before a toll is added.

“There has been a trend to drop a little bit,” project executive director Geoff Freer said of tunnel traffic counts. He said traffic over the Oak Street Bridge has declined about one per cent a year.

Jordan Bateman of the Canadian Taxpayers Federation said he doubts a 10-lane bridge is needed and is skeptical tolls will fully cover the costs without the government eating much of the debt.

Stone dismissed the objections.

“The naysayers did not build British Columbia and they will not build British Columbia,” Stone said. “Visionaries build British Columbia.”

B.C.’s longest bridge, upgrades along Highway 99

At three kilometres long, the new bridge at the Deas Island crossing will be the longest cable-stayed bridge in B.C. – 65 per cent longer than the Port Mann and 32 per cent longer than the Alex Fraser.

Its 210-metre high towers will be as tall as 60-storey buildings.

The project includes upgrades along 25 kilometres of Highway 99 from the Highway 91 interchange to Bridgeport Road in Richmond, with HOV/transit lanes running the length of the corridor.

It would add a multi-use pathway for cyclists and pedestrians.

New interchanges are planned at Steveston Highway, Westminster Highway and Highway 17A.

The bridge will run over top of the existing alignment and tower over Deas Island Regional Park.

Unlike the Port Mann Bridge, where a buildup of ice once fell and damaged vehicles, the cables will not cross over the roadway, and a similar snow and ice removal system will be installed.

The project also includes removal of the more than 55-year-old tunnel, which does not meet current earthquake standards.

The $3.5 billion cost estimate includes interest and tunnel decommissioning.

The Transportation Investment Corp. would run the bridge and tolls would be collected by TReO, using the same system as for the Port Mann.

The province claims the project will result in fewer idling vehicles and will therefore cut greenhouse gas emissions.

Other promised benefits include improved access across Highway 99 in Richmond, and an improved route off Highway 99 to Bridgeport Station for commuters switching to the Canada Line.

A 35 per cent cut in accidents is projected from wider lanes and shoulders and longer merge lanes.

A third round of public consultation is getting underway. For more info see masseytunnel.ca.

Just Posted

The Outdoor Recreation Council of B.C. says the province continues to invest too little in BC Parks, compared with public demand. (Special to The News)
Outdoor rec group decries parks funding

Golden Ears Park packed by record numbers of visitors

Community residents, businesses, and youth are all encouraged to complete economic development surveys. (The News files)
City of Maple Ridge asks for community input on economic development

Three surveys available online will help shape strategy for years to come

COVID-19. (Image courtesy CDC)
Schools in Maple Ridge, Pitt Meadows exposed to COVID-19

Davie Jones and Hammond elementary schools have confirmed cases

B.C. conservation officer Sgt. Todd Hunter said a black bear is believed to have killed local livestock. (THE NEWS/files)
Black bear believed to have killed miniature donkey in Maple Ridge

Trap set for predator that has been killing livestock near Webster’s Corners

The border crossing into the United States is seen during the COVID-19 pandemic in Lacolle, Que. on February 12, 2021. THE CANADIAN PRESS/Paul Chiasson
VIDEO: Border quarantine to soon lift for fully vaccinated Canadians

Eligible travellers must still take multiple COVID-19 tests

The former Kamloops Indian Residential School on the Tk’emlups te Secwépemc reserve. (Allen Douglas/Kamloops This Week)
Tk’emlups preparing for archaeological work at B.C. residential school site where remains found

The 215 graves are, to the band’s knowledge, undocumented deaths for which it is still collecting records

Fans watch the warm-up before Game 6 between the Toronto Maple Leafs and the Montreal Canadiens in NHL playoff hockey action Saturday, May 29, 2021 in Montreal. Quebec’s easing of COVID-19 restrictions will allow 2,500 fans to attend the game for the first time in fourteen months. THE CANADIAN PRESS/Ryan Remiorz
Two-thirds of Canadians say governments shouldn’t lift all COVID-19 restrictions

Poll reports Canadians who gained pandemic weight say they have gained 16 pounds on average

Paul Bernardo is shown in this courtroom sketch during Ontario court proceedings via video link in Napanee, Ont., on October 5, 2018. Teen killer and serial rapist Paul Bernardo is set for a parole hearing today. The designated dangerous offender, has been eligible for full parole for more than three years. Bernardo’s horrific crimes in the 1980s and early 1990s include for kidnapping, torturing and killing Kristen French and Leslie Mahaffy near St. Catharines, Ont. THE CANADIAN PRESS/Greg Banning
Killer rapist Paul Bernardo faces parole hearing today; victim families opposed

Designated dangerous offender has been eligible for full parole for more than three years.

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

People look over the damage after a tornado touched down in Mascouche, Que., north of Montreal, Monday, June 21, 2021. Dozens of homes were damaged and one death has been confirmed. THE CANADIAN PRESS/Ryan Remiorz
One dead and extensive damage as tornado hits Mascouche, Que., north of Montreal

Damage reported in several parts of the city, and emergency teams dispatched to sectors hardest hit

Chilliwack secondary school’s principal is apologizing after a quote equating graduation with the end of slavery in the U.S. was included in the 2020-2021 yearbook. (Screenshot from submitted SnapChat)
B.C. student’s yearbook quote equates grad to end of slavery; principal cites editing error

Black former student ‘disgusted’ as CSS principal apologizes for what is called an editing error

Skeena MLA Ellis Ross. (Photo by Peter Versteege)
BC Liberal leadership candidate condemns ‘senseless violence’ of Okanagan church fires

Skeena MLA Ellis Ross says reconciliation isn’t about revenge for past tragedies

A coroner’s inquest will be taking place at the Capitol Theatre in Port Alberni for the next week. (ELENA RARDON / ALBERNI VALLEY NEWS)
Teen B.C. mom who died following police custody recalled as ‘friend to many’

Police sent Jocelyn George to hospital after intoxication had gone ‘beyond the realm’ of normal detox

Most Read