Major traffic disruptions are expected when Pattullo Bridge is partly or completely shut down in much of 2016 and 2017.

Traffic chaos for 18 months during Pattullo Bridge work

TransLink will completely close bridge nights and weekends, cut to one lane each way weekdays and ban trucks

Commuters can brace for a year and a half of worsened congestion starting next spring when TransLink closes half the lanes of the Pattullo Bridge for major repairs and shuts down the entire crossing at night and on weekends.

For 18 months likely beginning next April, the already heavily congested bridge will be reduced from four lanes to two on weekdays – one in each direction – and heavy trucks will be banned, along with cyclists and pedestrians.

TransLink infrastructure management and engineering vice-president Fred Cummings acknowledged it will mean major disruptions for commuters and the congestion there will spill over to other routes as motorists avoid the Pattullo.

“It looks like it’s going to add, depending on the time of day, anywhere from five to 15 minutes at the minimum to people’s travel time if they try to go across the Pattullo on a weekday,” he said. “It’s also going to have impacts on the other crossings as far to the west as the Alex Fraser and possibly the Massey Tunnel as well.”

But he said the work must go ahead.

The 78-year-old bridge needs a $100-million deck rehabilitation and a seismic upgrade, including the addition of seismic bearings.

It’s currently in danger of failing from a moderate earthquake, ship collision or river erosion.

The Pattullo currently serves as the free alternative to the tolled Port Mann Bridge, carrying 75,000 vehicles a day.

But critics say that won’t be a reasonable option for people who refuse to pay the $3 Port Mann tolls during the Pattullo construction delays and closures.

B.C. Trucking Association president and CEO Louise Yako is urging the province to give at least trucks a break on tolls at the Port Mann to encourage them to use that crossing, rather than disrupting traffic further by diverting south to the Alex Fraser or Massey Tunnel to avoid tolls.

“They’re forcing trucks off of the Pattullo Bridge,” Yako said. “Hopefully there will be some recognition of that with a reduction of tolls on the Port Mann Bridge. It’s a lovely facility, it’s got the capacity and it’s being under-utilized by trucks today.”

She said toll relief would “encourage traffic to flow in the most rational way it can.”

Business leaders in both Surrey and New Westminster also urged the province last December to consider toll relief during the Pattullo work.

New Westminster Mayor Jonathan Coté agreed relaxed tolls would be helpful.

“Anything that can make using the Port Mann Bridge a more attractive option in terms of the tolling policy could assist,” he said. “Since they put the tolls in place, we’ve seen a significant shift in traffic to the Pattullo Bridge.”

A transportation ministry spokesperson said the Pattullo work is a year away and the government has no plans at this point to reduce tolls on the Port Mann.

Cummings said TransLink considered closing the bridge in an effort to get the work done much faster – perhaps in just a few months in the summer – but ruled it out after determining it would take a complete closure of eight to nine months.

“It just seemed impractical and the congestion would be just unbearable.”

Keeping the bridge partly open on weekdays will help minimize business impacts, he said, while balancing safety and traffic concerns.

The exact duration of the project will depend on how construction goes, what’s discovered during rehabilitation and the weather.

The decision to give nearly a year of advance warning is so people have as much time as possible to decide how they’ll respond, he said.

Cummings said the rehabilitation and seismic upgrades are required, even if the Metro Vancouver referendum on an extra 0.5 per cent sales tax for transit is approved, enabling plans to proceed for the replacement of the Pattullo with a $1-billion new bridge within seven to 10 years.

“Even if we had a decision yesterday on a solution for the replacement of the bridge this work would still go ahead.”

The Pattullo Bridge is 78 years old and needs $100 million of rehabilitation work even though there are also plans in the works to rebuild it at the cost of $1 billion. Black Press file photo.

Just Posted

UPDATE: Crash on Haney Bypass has lanes closed

Vehicle plunges down embankment in Maple Ridge

New rail underpass and overpass comes with costs

Pitt Meadows residents will see 0.75 per cent tax increase for rail crossings

Dewdney Trunk Road closed, vehicle crashes

Happened in early evening, injuries unknown

Court supports Maple Ridge role in tent city

Rejects Pivot application to allow people to return

City video updates Maple Ridge Leisure Centre re-do

Rusty support columns delaying project by a few months

Rents in most Canadian cities are unaffordable for lower-income earners: study

Roughly one-third of households, or 4.7 million, are renters

Chiefs honour Indigenous leader wrongfully hanged in B.C. 154 years ago today

Chief Joe Alphonse says they want his remains returned to his homeland in B.C.’s Cariboo region

Rare white ravens spotted again on Vancouver Island

Nature photographer Mike Yip said mysterious birds back in Coombs area

B.C. government seeks advice on reviving Interior forest industry

Public website opens as meetings start with community leaders

RCMP use helicopter and police dog to search for suspect on Sts’ailes First Nation

Small reserve near Agassiz surrounded by police vehicles, helicopter, ERT

Missing Vancouver Island woman believed to be on mainland

Rhonda Stevenson, 43, last seen July 13 in central Nanaimo

Psychics, drones being used to search for missing Chilliwack woman with dementia

Drones, psychics, dogs and more have been employed to help find Grace Baranyk, 86

Missing Greater Victoria man last seen in Vancouver’s Downtown Eastside

Jonah Donato, 40, travelled to the mainland in June

Most Read